Final Phase to Begin Late Summer!

The 3rd and final phase of the Water Street Reconstruction project is expected to commence late Summer 2024!

Phase 3 consists of final road works, including final lift of asphalt, raising structures, and landscaping. Work will take place on:

  • Water Street between Concession Street and Bridge Street;
  • Concession Street between Water Street and Queen Street;
  • Reid Street between Water Street and Queen Street;
  • King Street from Water Street Queen Street.

Once construction begins, working hours are expected to be 7:00am to 5:30pm Monday through Friday, with occasional Saturday work if production is lost due to inclement weather or other factors. Accurex will also be setting up their construction trailer again at the Lakefield Marina.

The road will be intermittently closed to through traffic (local traffic only).