Will there be road access during construction?

    Access to local traffic only (residents) will be maintained as much as possible. If there are any full road closures required for brief periods, notice will be provided 24 hours in advance where possible.

    Will there be impacts to adjacent private properties, driveways etc.?

    Services and amenities will be constructed on the public right-of-way. Any existing driveways on the public right-of-way or areas impacted on private lands will be replaced/repaired.

    Will garbage and recycling collection be impacted?

    Garbage and recycling should be put out as normal. Accurex will advise waste services of the construction.

    Will my water service be impacted?

    Temporary water services will be installed to ensure that residents continue to have access to the municipal water system.