April → October 2022

Phase 1

Note: The 1st area of construction will start at Reid Street to just past Hendren’s Funeral Home. This area will be completed 1st and a licenced archeologist will be overseeing the excavation of this section of construction due to the presence of the pioneer cemetery.

Water Street (from Concession Street to just before Reid Street):

  • New watermain 
  • Storm water
  • New roadway (1st lift) and curb and gutter
  • Layby parking beside St. Paul’s Church
  • Defined parking beside boat launch
  • New sidewalk in front of condos to King Street and replacing existing sidewalk
  • Boat launch improvements (upland apron and in-water) 
    • Note: pending permit approval, in-water boat launch works to take place commencing late fall of 2022 and be completed by spring of 2023.

King Street:

  • New water and sanitary main 
  • Storm water
  • New roadway (1st lift) and curb and gutter
  • Replacement of existing sidewalk
April → November 2023

Phase 2

Water Street (from Reid Street to Bridge Street):

  • New watermain 
  • Storm water
  • New roadway (1st lift) and curb and gutter
  • Designated parking at bridge
  • Replacement of existing sidewalk

Reid Street:

  • New water main from Charlotte to Water Street
  • Some minimal sanitary work
  • New roadway and sidewalk re-install
August → October 2024

Phase 3

All final adjustments, and road works.

Water Street, Concession Street, Reid Street and King Streets:

  • Final lift of asphalt, raising structures, and landscaping.